PM FPX 4020 Assessment 3 Work Breakdown Structure example

Reviewed by Rupert Danvers, MBA Integration and Scope Management Capella University Free custom sample in 24 to 48h

This PM FPX 4020 Assessment 3 sample paper is a work breakdown structure for the veterinary hospital relocation that decomposes deliverables rather than listing activities. It completes Capella PM FPX 4020, Integration and Scope Management, in the BS in Business, Project Management, catalog code PM-FPX4020. The paper presents the full numbered outline first and applies a stopping test at the bottom level. It uses numbering that proves the hierarchy, makes sure each parent holds all its children and writes a dictionary entry for every work package. It explains the level of detail by area, why these parents were chosen and what is deliberately left out of the structure.

CoursePM FPX 4020 Integration and Scope Management
AssessmentAssessment 3
Paper typeWork breakdown structure
LengthAbout 1,110 words, 5 pages
FormatAPA 7 student paper
SchoolCapella University
ProgramBS in Business, Project Management
UpdatedSeptember 2026

Free sample paper for PM FPX 4020 Assessment 3

1

A Work Breakdown Structure for a Veterinary Hospital Relocation: Deliverables Decomposed, a Stopping Test at the Bottom, Numbering That Proves the Hierarchy, Parents Holding All Their Children, and a Dictionary Entry for Every Package

Student Name

Capella University

PM FPX 4020: Integration and Scope Management

Instructor Name

Month Day, Year

What this part is doingThe title names the structure and its features. WBS papers are judged on decomposition and completeness, so both are named.
2

Deliverables Decomposed, Not Activities Listed

The structure breaks the project's deliverables into smaller deliverables, not into a list of activities. Each element is a noun: "radiology room shielding," not "install shielding." Activities belong in the schedule, which will be built from the work packages. The Project Management Institute (2019) describes the work breakdown structure as a deliverable-oriented decomposition of the total scope, and the structure below follows that rule.

A Stopping Test at the Bottom

Decomposition stops when a package passes three tests: it can be assigned to one responsible party; its cost and duration can be estimated with reasonable confidence; and its completion can be verified with an acceptance criterion. For example, "renovated building" fails the first test because several trades work on it; "radiology room shielding" passes all three, since one subcontractor does it, it has a quoted price, and a physicist's certificate verifies it.

The Structure With Numbering That Proves the Hierarchy

1 Maple Ridge Relocation 1.1 Project management 1.1.1 Project plan and baselines 1.1.2 Status reports and site meeting minutes 1.1.3 Closeout report 1.2 Design and approvals 1.2.1 Construction drawings and specifications 1.2.2 City building permit 1.2.3 State veterinary premises permit 1.3 Renovated building 1.3.1 Demolition 1.3.2 Framing, walls, and doors 1.3.3 Mechanical, electrical, and plumbing systems 1.3.4 Radiology room shielding 1.3.5 Finishes and kennel flooring 1.3.6 Certificate of occupancy 1.4 Equipment 1.4.1 Surgical and anesthesia equipment 1.4.2 Digital radiography system 1.4.3 Kennel runs and cages 1.5 IT and phones 1.5.1 Network cabling and wireless 1.5.2 Phone system 1.5.3 Workstations and practice software moved 1.6 Move and opening 1.6.1 Client notification 1.6.2 Moved equipment, records, and supplies 1.6.3 Opening day readiness Each number shows its parent: 1.3.4 belongs to 1.3, which belongs to 1.

What this part is doingThe numbering encodes the hierarchy. Scorers reward structures whose numbers show parent and child.
3

Parents That Hold All Their Children

Each parent's cost equals the sum of its children, and together the children contain all of the parent's scope. 1.1 Project management, 40,500 dollars: 8,000 plus 28,500 plus 4,000. 1.2 Design and approvals, 95,000 dollars: 70,000 plus 18,000 plus 7,000. 1.3 Renovated building, 850,000 dollars: 60,000 plus 190,000 plus 330,000 plus 45,000 plus 215,000 plus 10,000. 1.4 Equipment, 180,000 dollars: 72,000 plus 68,000 plus 40,000. 1.5 IT and phones, 90,000 dollars: 38,000 plus 22,000 plus 30,000. 1.6 Move and opening, 35,000 dollars: 3,000 plus 27,000 plus 5,000. Level 1 total: 1,290,500 dollars, which, with contingency of 84,500 dollars and management reserve of 60,000 dollars held outside the structure, gives the 1,435,000 dollar budget. If the children do not add up to the parent, either work is missing or work is counted twice.

A Dictionary Entry for Every Package

Each entry gives the description, responsible party, acceptance, and estimate. 1.1.1 Plan and baselines: scope, schedule, cost, risk, and communication plans; practice manager; sponsor approval; 8,000 dollars. 1.1.2 Status reports and minutes: weekly site meeting minutes and monthly reports to the sponsor; practice manager; issued within two days of each meeting; 28,500 dollars. 1.1.3 Closeout report: final cost, lessons learned, archived records; practice manager; sponsor acceptance; 4,000 dollars. 1.2.1 Drawings and specifications: architect; stamped and approved by sponsor; 70,000 dollars. 1.2.2 City building permit: architect submits; permit issued; 18,000 dollars in fees. 1.2.3 State premises permit: practice manager; permit issued; 7,000 dollars including inspection. 1.3.1 Demolition: contractor; interior removed to the lines on the drawings; 60,000 dollars. 1.3.2 Framing, walls, and doors: contractor; inspected by architect; 190,000 dollars. 1.3.3 Mechanical, electrical, and plumbing: contractor and subcontractors; city rough-in and final inspections passed; 330,000 dollars. 1.3.4 Radiology shielding: shielding subcontractor; physicist certificate; 45,000 dollars. 1.3.5 Finishes and kennel flooring: contractor; staff punch list closed; 215,000 dollars. 1.3.6 Certificate of occupancy: contractor coordinates; certificate issued; 10,000 dollars. 1.4.1 Surgical and anesthesia equipment: vendor; installed, tested, staff trained; 72,000 dollars. 1.4.2 Digital radiography: vendor; installed, tested, registered; 68,000 dollars. 1.4.3 Kennel runs and cages: vendor; installed and anchored; 40,000 dollars. 1.5.1 Cabling and wireless: IT vendor; coverage test passed in every room; 38,000 dollars. 1.5.2 Phone system: IT vendor; all extensions tested; 22,000 dollars. 1.5.3 Workstations and software moved: IT vendor; every workstation connected to practice software; 30,000 dollars. 1.6.1 Client notification: client service supervisor; notices sent 60, 30, and 7 days before move; 3,000 dollars. 1.6.2 Moved items: movers and staff; move inventory checked complete; 27,000 dollars. 1.6.3 Opening readiness: practice manager; opening checklist complete, including supplies stocked and staff walkthrough held; 5,000 dollars.

What this part is doingEvery package has an owner, acceptance test, and estimate. Scorers reward complete WBS dictionaries.
4

Level of Detail by Area

The structure goes deeper where the project carries more risk and money. The renovated building, at 850,000 dollars, is broken into six packages, one per trade grouping, because change orders and inspections happen at that level. Project management and move and opening stay shallower, because their work is done by practice staff whose tasks are tracked in the schedule rather than in separate packages. Uneven depth is intentional: it follows where control is needed, not a rule that every branch must have the same number of levels.

Why These Parents

The six level-2 elements follow how the work will be contracted and managed. Design and approvals sit together because the architect drives both. The renovated building is one parent because one contractor delivers it under one contract. Equipment and IT are separate parents because different vendors supply them on different timelines. Move and opening is separate because practice staff do most of it, not contractors. Organizing by who delivers makes each parent easy to assign and track.

What Is Not in the Structure

Items excluded from scope, such as the second location, landscaping, and disposal of old equipment, do not appear in the structure. The structure contains all of the project's scope and nothing else, which is what makes it useful for checking whether a new request is part of the project: if it cannot be placed under an existing package, it is a change and goes to the change log for a decision.

How the Structure Will Be Used

The schedule will define activities for each package, the budget will track cost by package, and the change log will record which package each approved change affects.

Conclusion

The structure decomposes the relocation into 21 deliverable-based work packages under six parents, stops where one party can own, estimate, and verify each package, numbers every element to show its parent, and reconciles each parent to its children and the total to the budget. Every package has a dictionary entry.

5

References

Project Management Institute. (2019). Practice standard for work breakdown structures (3rd ed.). Project Management Institute.

PM FPX 4020 Assessment 3 instructions, in plain terms

The final assessment in PM FPX 4020 asks you to decompose the project scope into a work breakdown structure. You break each deliverable from the scope statement into smaller components until you reach work packages that can be estimated and assigned, number the elements to show the hierarchy, check that each parent is fully covered by its children, write a dictionary entry for each work package describing its content, owner and acceptance, and explain your decomposition logic. The structure should be deliverable-oriented, following the hundred percent rule. The PMI Practice Standard for Work Breakdown Structures and scope management texts support the work.

How the PM-FPX4020 Assessment 3 example is put together

The example presents the hierarchy before it explains itself. The numbered outline comes first so a reader can see the whole shape on one page, with the coding scheme visible and the levels consistent. A short passage then states the decomposition logic: deliverable-oriented branching, the rule that a parent contains all of its children and nothing else, and the stopping test used at the bottom, which is whether the package can be estimated, assigned and verified. The dictionary follows, one entry per work package, each carrying description, owner role, deliverable parent and acceptance test. A verification section walks two branches upward to show that no work was invented and none dropped out. The closing paragraph names the branch that will be hardest to estimate and says why, which reads as judgment rather than compliance.

Reading the PM FPX 4020 Assessment 3 scoring guide

Marks go to the decomposition, the stopping point, the numbering, the hundred percent rule, the dictionary and the explanation. Decomposition reaches Distinguished when the structure breaks down deliverables, not activities. The stopping point scores higher when a test is stated, such as a package that one person can own and estimate. Numbering earns credit when it shows the hierarchy consistently. The hundred percent rule is judged on whether each parent is completely covered by its children, with nothing missing or extra. The dictionary should have an entry for every package. The explanation should defend the chosen parents. Distinguished structures could be handed straight to scheduling and costing.

PM FPX 4020 Assessment 3 help from the desk

Work breakdown structures often become to-do lists of activities, like "call movers," instead of deliverables, like "moving services contract." Another weakness is decomposing some branches deeply and others barely at all without explaining why. Numbering is inconsistent, so the hierarchy is unclear. Children do not add up to their parent, which leaves work out. The dictionary is missing or covers only a few packages. Project management work itself is left out. Presenting the outline first, then checking each parent against its children and writing one dictionary entry per package, produces a structure that supports the schedule and cost work in PM FPX 4030.

Get a PM FPX 4020 Assessment 3 example written to your instructions

Send the Assessment 3 instructions and the scoring guide from your PM FPX 4020 courseroom, plus the scope statement the structure has to decompose. We write a custom example to those criteria, with numbered levels, estimable packages and a dictionary entry for each, and return it in 24 to 48 hours. The first custom sample is free. The paper above is an original model document written by our desk, not a submitted student paper and not an official Capella University document.

More PM FPX 4020 papers and BS in Business, Project Management samples

PM FPX 4020 Assessment 3 questions, answered

How far down should the structure go?

Until a package can be estimated with confidence, assigned to one owner and verified when finished. Many sections describe a guideline in reporting-period or effort terms, so check yours. Depth does not have to match across branches: a complex deliverable can justify four levels while a simple one stops at two, provided you say why.

Should project management itself appear in the structure?

Usually yes, as its own level two element covering planning, meetings, reporting and closeout. That work consumes real effort and real money, and leaving it out means the budget built from this structure will be short. Give it packages like any other branch, with owners and dictionary entries, rather than a single undefined heading.

Does it need to be a chart or is an outline acceptable?

Check your instructions, since some sections specify a graphical tree and others accept an indented outline. Either presentation can earn full credit if the numbering is consistent and the levels are clean. What no presentation rescues is a structure decomposed by activity, so settle the logic first and choose the format afterward.

Where can I find a free PM FPX 4020 Assessment 3 sample paper?

This page shows the complete breakdown of the hospital move, with deliverables decomposed, a stopping test at the bottom, numbering that proves the hierarchy and a dictionary entry for every package.

What is the hundred percent rule in PM FPX 4020 Assessment 3?

The rule that the work breakdown structure includes all the work in the scope and nothing outside it, and that each parent's children together cover the whole of the parent.