PM FPX 4020 Assessment 1 Project Charter example

Reviewed by Rupert Danvers, MBA Integration and Scope Management Capella University Free custom sample in 24 to 48h

This PM FPX 4020 Assessment 1 sample paper is a project charter for the veterinary hospital relocation, the document that formally authorizes the project and the manager who will run it. It was written for Capella PM FPX 4020, Integration and Scope Management, a course in the BS in Business, Project Management, with the catalog code PM-FPX4020. The paper opens with the title and purpose, names a sponsor with real authority and states the project manager's authority as clear limits on spending and staffing. It writes success criteria someone can verify, keeps scope at charter level, sets milestones and a summary budget, and covers governance, high-level risks, key stakeholders and a signature block.

CoursePM FPX 4020 Integration and Scope Management
AssessmentAssessment 1
Paper typeProject charter
LengthAbout 1,120 words, 5 pages
FormatAPA 7 student paper
SchoolCapella University
ProgramBS in Business, Project Management
UpdatedSeptember 2026

Free sample paper for PM FPX 4020 Assessment 1

1

A Project Charter for a Veterinary Hospital Relocation: A Sponsor With Real Authority, the Manager's Authority Stated as Limits, Success Criteria Someone Can Verify, Scope Kept at Charter Level, and a Signature Block That Closes It

Student Name

Capella University

PM FPX 4020: Integration and Scope Management

Instructor Name

Month Day, Year

What this part is doingThe title names the project and the charter's features. Charters are judged on authority and verifiability, so both lead.
2

Project Title and Purpose

Project: Maple Ridge Animal Hospital Relocation. Purpose: move the practice from leased space at 220 Elm Street, which it has outgrown, to a building it owns at 1450 Prairie Road, renovated for veterinary care. The practice now has four exam rooms and a waitlist of nine days for non-urgent appointments; the Elm Street lease ends July 31 and the landlord will not expand the space. The new building will provide six exam rooms, a proper surgery suite, and room to add a second surgeon.

A Sponsor Named With Real Authority

Sponsor: Dr. Karen Walsh, owner of Maple Ridge Animal Hospital. Dr. Walsh owns the practice and the new building, signed the renovation loan, and has sole authority to approve the project budget, sign contracts with the architect and contractor, and change the opening date. She can say yes or no to any decision on this project without asking anyone else. The Project Management Institute (2021) describes the sponsor as the person who provides resources and support and is accountable for enabling success; a sponsor without authority over money and contracts cannot play that role.

The Manager's Authority Stated as Limits

Project manager: Jennifer Moore, practice manager. Her authority is stated as specific limits so there is no doubt about what she can decide alone. She may approve purchases within approved budget lines up to 10,000 dollars per item. She may approve construction change orders up to 5,000 dollars each and up to 20,000 dollars in total; anything above requires the sponsor. She may assign practice staff to project tasks for up to six hours a week each, with the agreement of their supervisor. She may not use the management reserve, change the opening date, change the design after the design freeze, or sign contracts; these require the sponsor. A manager told she has "authority to manage the project" has no idea what she can sign.

What this part is doingAuthority is written as limits in dollars and decisions. Scorers reward charters that make authority concrete.
3

Success Criteria Someone Can Verify

The project succeeds if each criterion below is met, and each can be checked by someone outside the project. The first patient appointment at 1450 Prairie Road occurs on or before June 1. Verified by the appointment system. Total project cost does not exceed 1,435,000 dollars. Verified by the final cost report reconciled to invoices. A certificate of occupancy, the state veterinary premises permit, and radiation equipment registration are issued before the first patient. Verified by the documents. The practice is closed for no more than two business days during the move, and no scheduled surgery is canceled because of the move. Verified by the appointment system. The building contains six exam rooms, one surgery suite with separate prep area, and kennels able to hold 30 animals, all confirmed during the closing walkthrough.

Scope Kept at Charter Altitude

The charter describes scope at a high level; detail belongs in the scope statement. In scope: design and permits; renovation of the building; new surgical, anesthesia, radiography, and kennel equipment; network, phones, and workstations; moving existing equipment, records, and supplies; client notification; and opening. Out of scope: the planned second location, sale of equipment not moved, changes to services offered, and landscaping beyond what the city requires.

Milestones

Design complete and frozen: November 3. City building permit issued: December 15. Construction complete: April 6. IT and phones installed: April 27. Certificate of occupancy: May 4. Target opening: May 11. Required opening: June 1.

Summary Budget

Design and permits, 95,000 dollars; renovation contract, 850,000 dollars; equipment, 180,000 dollars; IT and phones, 90,000 dollars; move and opening, 35,000 dollars; project management staff time, 40,500 dollars; contingency, 84,500 dollars; management reserve, 60,000 dollars. Total: 1,435,000 dollars.

What this part is doingThe budget is summarized by category and totals correctly. Scorers reward charters whose summary figures add up.
4

Governance

The project manager reports to the sponsor weekly after the site meeting and monthly in writing. Decisions above the project manager's limits go to the sponsor, who commits to answering within five business days so that the contractor is not left waiting on a decision that holds up work.

High-Level Risks

Permit review longer than six weeks; hidden conditions found during demolition; equipment lead times longer than 12 weeks; the Elm Street lease ending before the move if the landlord's verbal extension offer is not honored.

Key Stakeholders

Associate veterinarians and technicians, who will use the building; clients, who need to know where to go; the general contractor and architect; the city's permit office and the state board that licenses veterinary premises; the Elm Street landlord; and the practice's lender.

Why the Practice Manager Leads the Project

The owner considered hiring an outside project manager but chose the practice manager, Jennifer Moore, because she knows the practice's workflow, staff, and vendors, and will run the new building afterward. The trade-off is her time: she will spend about 40% of her week on the project, and the lead technician and client service supervisor will take on some of her daily duties until the move. The charter's limits on her authority are set to match the decisions she can make quickly without disrupting the owner's clinical schedule.

Assumptions Behind the Charter

The charter assumes that the design can be frozen by November 3, that the contractor selected will hold its bid price, and that the Elm Street landlord will allow a short extension if needed. The project manager will confirm the last assumption in writing within two weeks of authorization.

How the Charter Will Be Used

The charter authorizes the project manager to begin planning and spend within the limits above. It is the reference for any dispute about authority or success. It will not be revised for ordinary changes, which go through the project's change log; it will be revised only if the sponsor changes the purpose, the budget total, or the required opening date.

Signature Block That Closes It

Approved by: Dr. Karen Walsh, Owner and Sponsor. Signature and date: ____________. Accepted by: Jennifer Moore, Practice Manager and Project Manager. Signature and date: ____________. The project is authorized on the date of the sponsor's signature. Until then, no contract may be signed and no project spending may begin. The signature is what turns the document from a proposal into an authorization.

Conclusion

The charter authorizes the Maple Ridge relocation with Dr. Walsh as sponsor holding full authority, gives Jennifer Moore stated spending and change limits, sets five verifiable success criteria, keeps scope at a high level, summarizes a 1,435,000 dollar budget, and closes with signatures that authorize the work.

5

References

Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.). Project Management Institute.

PM FPX 4020 Assessment 1 instructions, in plain terms

The first assessment in PM FPX 4020 asks you to write a charter that authorizes a project. You state the purpose and business case, name the sponsor and the project manager and define the manager's authority, set measurable objectives and success criteria, describe scope at a high level, list major milestones and a summary budget, identify key stakeholders and high-level risks, and provide for approval. The charter is short and decisive; detail belongs in later planning documents. The PMBOK Guide's description of the charter as the document that formally authorizes a project, along with integration management texts, supports the work.

How the PM-FPX4020 Assessment 1 example is put together

The example follows the order a charter is normally read in. Purpose and business case come first, since the reader approving the document wants the reason before the mechanics. The objectives and success criteria follow, written so that someone at the end of the project could declare it met or not met. High-level scope arrives next, bounded but not decomposed, because decomposition is the third assessment. The milestone list gives dates at summary level only. Then comes the section that most versions skip: the authority statement, which fixes a spending limit, a staffing limit and the change threshold above which the sponsor decides. Risks, assumptions and constraints follow in separate blocks. The signature block closes the document, with the sponsor above the manager, since the authority runs downward from the person who owns the budget.

PM FPX 4020 Assessment 1 scoring guide: what Distinguished looks like

Capella's scoring guide rates the purpose, the sponsor, the manager's authority, the success criteria, the scope, the milestones and budget, and the approval. The sponsor reaches Distinguished when the person named can actually commit money and people, such as the hospital's owner rather than an office manager. Authority scores higher when stated as limits, like approving spending up to a set amount without the sponsor. Success criteria earn credit when someone at the end could check each one. Scope is judged on whether it stays high level, since a charter crowded with detail becomes hard to approve. Milestones and budget should be summary figures. The signature block closes the charter formally. Proficient charters include every section; Distinguished ones make authority and success unmistakable.

PM FPX 4020 Assessment 1 help from the desk

Charters often name a sponsor who has no power to fund the project, which leaves the project manager without backing when decisions are needed. Another weakness is describing the manager's authority vaguely, like "will lead the project," with no spending or staffing limits. Success criteria are aspirations, such as "a smooth move," that no one could verify. Scope sprawls into task lists that belong in the scope statement. The budget is a detailed breakdown instead of a summary. The signature block is missing, so nothing is actually authorized. Keeping the charter to a few pages, with authority stated in dollar limits and each success criterion written as a checkable statement, gives the document the force it is meant to have.

Get a PM FPX 4020 Assessment 1 example written to your instructions

Send the Assessment 1 instructions and the scoring guide from your PM FPX 4020 courseroom, plus any template or case scenario your section supplies. We write a custom example to those criteria, with the authority statement and signature block built in, and return it in 24 to 48 hours. The first custom sample is free. The paper above is an original model document written by our desk, not a submitted student paper and not an official Capella University document.

More PM FPX 4020 papers and BS in Business, Project Management samples

PM FPX 4020 Assessment 1 questions, answered

What does an authority statement actually say?

It gives the manager a number and a boundary. A worked example reads along the lines of committing up to a stated amount per purchase without further approval, assigning staff from named departments with their supervisors informed, and referring any change beyond a stated cost or schedule impact to the sponsor. Sections vary, so match the level your instructions describe.

Can the sponsor be me?

Not usefully. A charter works because someone with budget authority authorizes someone else to spend it, and a document where both roles are the same person has no authorization in it. Name a role that plausibly controls the funding, such as an operations director or a division head, and keep the manager appointment separate from it.

How detailed should the charter budget be?

An order of magnitude with the basis stated, not a line-item estimate. A charter is written before detailed planning, so a range with the assumption behind it is honest and a precise figure is not. Say what the number rests on, whether a similar past project or a vendor quotation, and leave the detailed build to the cost course.

Where can I find a free PM FPX 4020 Assessment 1 sample paper?

Read the whole relocation charter here, including a sponsor who has real authority, the manager's authority stated as limits, verifiable success criteria and a signature block. The scope statement follows.

What does a project charter authorize in PM FPX 4020 Assessment 1?

It formally starts the project and gives the project manager authority to use organizational resources. Without an approved charter, the manager has no standing to commit money or people.