Free sample paper for PM FPX 4040 Assessment 1
A Responsibility Assignment Matrix for a Veterinary Hospital Move: One Accountable Role per Row, Rows Taken From the Deliverables, Columns That Are Roles, Consulted Marks Used Sparingly, and Notes That Defend the Assignments
Student Name
Capella University
PM FPX 4040: Human Resources and Motivation Management
Instructor Name
Month Day, Year
Purpose
Maple Ridge Animal Hospital's move to its renovated Prairie Road building involves the practice owner, the practice manager, clinical staff, an architect, a general contractor, and several vendors. Confusion about who decides and who does the work is a common cause of delay on small projects where everyone knows each other and assumes someone else is handling it. The matrix makes responsibilities explicit. The Project Management Institute (2017) describes the RACI chart as a common form of responsibility assignment matrix showing who is responsible, accountable, consulted, and informed for each item.
Columns Are Roles, Not People
The columns are roles, so the matrix still works if a person changes: Sponsor (practice owner); Project Manager (practice manager); Clinical Lead (lead veterinary technician); Architect; General Contractor; Equipment Vendors; IT Vendor; Client Service Supervisor. Where one person holds a role today, the name appears only in the project directory, not in the matrix.
Rows Taken From the Deliverables
Rows come from the work breakdown structure's deliverables, so every deliverable has an owner and nothing is assigned that is not in scope. Letters: R, responsible for doing the work; A, accountable for the result, one per row; C, consulted before decisions; I, informed after. Construction drawings: Architect R; Sponsor A; Clinical Lead C; Project Manager I. City building permit: Architect R; Project Manager A; Sponsor I. State premises permit: Project Manager R and A; Clinical Lead C. Renovated building: General Contractor R; Sponsor A; Architect C; Project Manager I. Radiology shielding certification: General Contractor R; Project Manager A; Architect I. Surgical and anesthesia equipment: Equipment Vendors R; Project Manager A; Clinical Lead C; Sponsor I. Digital radiography system: Equipment Vendors R; Project Manager A; Clinical Lead C. Kennel runs: Equipment Vendors R; Project Manager A; Clinical Lead C. Network, phones, and workstations: IT Vendor R; Project Manager A; Client Service Supervisor C. Client notification: Client Service Supervisor R; Project Manager A; Sponsor C. Move of equipment, records, and supplies: Project Manager R and A; Clinical Lead R; Client Service Supervisor R; Sponsor I. Opening day readiness: Project Manager R; Sponsor A; Clinical Lead C; Client Service Supervisor C. Project plan, reports, and closeout: Project Manager R; Sponsor A. Two A's in one row mean that when something goes wrong, both people will think the other was watching.
One Accountable Role per Row
Every row has exactly one A. Where it was tempting to share accountability, a choice was made. For the renovated building, both the sponsor and the project manager care about the result, but the sponsor holds the contract with the contractor and approves payments, so the sponsor is accountable and the project manager is informed and manages day to day. For equipment, the project manager is accountable because she places orders within her authority, even though the clinical lead cares most about the choice.
Consulted Marks Used Sparingly
Consulted marks are used only where a person's input would change the decision. The clinical lead is consulted on drawings, equipment, and opening readiness because clinical workflow shapes those decisions. The client service supervisor is consulted on phones and on client notification because the front desk uses them. The architect is consulted on the renovated building but not on equipment, because equipment choices do not affect the building beyond what the drawings already provide. Too many C marks would slow decisions and make every choice a meeting.
Notes That Defend the Assignments
Note 1: the architect is responsible for obtaining the building permit because the city requires a licensed professional to submit drawings, but the project manager is accountable because a late permit harms the practice, not the architect. Note 2: the general contractor is responsible for radiology shielding, but the project manager is accountable because the practice hires the physicist who certifies it and holds the state registration. Note 3: the move has three R's because the work is shared among clinical staff, front desk staff, and the project manager; the single A keeps one person in charge of the move plan. Note 4: the sponsor is informed, not consulted, on most equipment, because she delegated equipment decisions within budget to the project manager and clinical lead.
How the Matrix Was Built
The project manager drafted the matrix from the work breakdown structure, then reviewed it in a one-hour meeting with the sponsor, the clinical lead, and the architect. Two changes came from that meeting. The architect asked to be consulted on radiology shielding rather than only informed, because shielding affects wall construction, and the change was made in the construction phase rather than the matrix row for certification. The clinical lead asked to be responsible, not only consulted, for the move of clinical equipment, because she knows how each item must be packed; the move row was updated.
Gaps the Matrix Revealed
Building the matrix revealed two gaps. No one had been assigned to arrange emergency coverage with the county emergency hospital during the move; it is now a task under opening readiness, with the project manager responsible. No one owned the transfer of controlled substances, which must be logged; the practice owner, as the registrant, is now accountable, with the lead technician responsible for the count.
Informed Marks and How Information Flows
Informed marks are matched to the communication plan: anyone marked I on a row receives the weekly site meeting minutes or the monthly report, depending on their role. This avoids the problem of people being marked informed with no actual route by which information reaches them.
When the Matrix Is Challenged
When someone questions an assignment, the matrix is the starting point, not the final word. The project manager can propose a change, but only the sponsor approves changes to accountable roles, since accountability affects who answers to her. This keeps the matrix stable without making it rigid.
Using the Matrix
The matrix is reviewed at the kickoff meeting, attached to the project plan, and consulted whenever a question of who decides arises. It is updated if roles change, and each update is dated and sent to everyone named in the matrix so that no one works from an old version.
Conclusion
The matrix assigns roles across 13 deliverable rows, uses role-based columns, gives each row one accountable party, limits consulted marks to where input changes decisions, and explains four assignments that might otherwise be questioned.
References
Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK guide) (6th ed.). Project Management Institute.
What the PM FPX 4040 Assessment 1 instructions ask for
The first assessment in PM FPX 4040 asks you to build a responsibility assignment matrix for a project. You list deliverables or work packages as rows, taken from the work breakdown structure, list roles as columns, including the sponsor and any vendors, and mark who is responsible, accountable, consulted and informed for each row. Each row should have exactly one accountable role. You then explain the key assignments, identify gaps or overloads the matrix reveals and describe how it will be maintained. Texts on project human resource management and the RACI model support the work.
How this PM FPX 4040 Assessment 1 example is built
The example builds the grid from documents that already exist. Rows are lifted from the work breakdown so the matrix covers the project rather than a separate idea of it, and columns are drawn from the roles the organization actually has, including the sponsor and any external vendor. The legend is defined before the grid appears, since a reader has to know what each letter means to check the assignments. The grid follows, and after it comes the part that earns most of the credit: a set of notes justifying the assignments where a reader would raise an eyebrow, such as accountability sitting with a role that does none of the work. A conflict section says what happens when a responsible role and an accountable role disagree. The closing paragraph names the role carrying the heaviest load.
Reading the PM FPX 4040 Assessment 1 scoring guide
Capella's scoring guide rates the rows, the columns, the assignments, the single accountable role, the use of consulted and informed marks, and the supporting explanation. Rows reach Distinguished when taken from the deliverables, so the matrix covers the whole project. Columns score higher when they are roles, which keeps the matrix valid when people change. Assignments earn credit when each row has exactly one accountable role, since shared accountability means no accountability. Consulted marks are judged on restraint, because every consulted person adds time to a decision. Informed marks should reflect how information actually needs to flow. The explanation should defend key choices and name gaps, such as one role carrying too many responsibilities. Proficient matrices are complete; Distinguished ones show the thinking behind them.
PM FPX 4040 Assessment 1 help from the desk
Responsibility matrices often put two or three accountable marks on important rows, which leaves nobody truly answerable. Another weakness is using people's names as columns, so the matrix breaks the moment someone leaves. Rows are invented instead of drawn from the work breakdown structure, so some work is missing. Consulted marks appear everywhere, slowing every decision. The matrix is presented with no explanation. Overloaded roles go unnoticed. Counting the marks in each column after the grid is built reveals who carries too much, and a short note under the matrix explaining the hardest assignments shows the scorer that each choice was deliberate.
Get a PM FPX 4040 Assessment 1 example written to your instructions
Send the Assessment 1 instructions and the scoring guide from your PM FPX 4040 courseroom, plus the deliverable list and the roles your project has available. We write a custom example to those criteria, with single accountability per row and the assignments defended, and return it in 24 to 48 hours. The first custom sample is free. The paper above is an original model document written by our desk, not a submitted student paper and not an official Capella University document.
More PM FPX 4040 papers and BS in Business, Project Management samples
- PM FPX 4040 Assessment 2: Staffing Management Plan
- PM FPX 4040 Assessment 3: Motivation Analysis
- PM FPX 4050 Assessment 1: Stakeholder Analysis
- PM FPX 4030 Assessment 1: Schedule Network Diagram
- PM FPX 4060 Assessment 1: Risk Identification Memo
- PM FPX 4020 Assessment 1: Project Charter
PM FPX 4040 Assessment 1 questions, answered
Can one role be both responsible and accountable?
Yes, and on a small project it happens often. A team lead who both produces a deliverable and answers for it carries both marks on that row, which is fine. What breaks the matrix is two different roles both marked accountable, because the row then has no single point of answer and the criterion reading for clear ownership finds none.
How many rows should the matrix have?
As many as your deliverable list has, which usually means the work package level rather than every activity. A matrix with two hundred rows becomes unreadable and a matrix with four says nothing about who does what. If your breakdown structure is large, roll up to the level where each row still has a genuine owner.
Does the matrix need supporting narrative?
Almost always. The grid satisfies the deliverable criterion but the analysis criteria need prose: why accountability sits where it does, how a manager without formal authority secures cooperation from a role reporting elsewhere, and what happens when two roles disagree. Check your scoring guide, since the narrative is often worth more than the table itself.
Where can I find a free PM FPX 4040 Assessment 1 sample paper?
This page carries the complete RACI matrix for the hospital move: rows from the deliverables, role columns, one accountable role per row, sparing consulted marks and notes defending each assignment.
Can one role be responsible and accountable in PM FPX 4040 Assessment 1?
Yes, on smaller tasks the same role often does the work and answers for it. What the matrix must avoid is more than one accountable role on a row.