| Course | PM FPX 4030 Scheduling, Cost, and Quality Management |
|---|---|
| Assessment | Assessment 1 |
| Paper type | Schedule network diagram |
| Length | About 1,180 words, 5 pages |
| Format | APA 7 student paper |
| School | Capella University |
| Program | BS in Business, Project Management |
| Updated | September 2026 |
Free sample paper for PM FPX 4030 Assessment 1
Scheduling a Veterinary Hospital Relocation: Activities Traced to Work Packages, Dependencies Given With Reasons, Forward and Backward Passes Shown, the Critical Path Derived, and Near-Critical Chains Flagged
Student Name
Capella University
PM FPX 4030: Scheduling, Cost, and Quality Management
Instructor Name
Month Day, Year
Activities Traced to Work Packages
Each activity comes from the work breakdown structure, with durations in weeks from estimates by the architect, contractor, and vendors. A, prepare construction drawings, from 1.2.1: 8 weeks. B, obtain city building permit, from 1.2.2: 6 weeks. C, select and order equipment, from 1.4: 4 weeks. D, equipment manufacture and delivery, from 1.4: 12 weeks. E, bid and award construction contract, supporting 1.3: 4 weeks. F, renovation construction, from 1.3.1 to 1.3.5: 16 weeks. G, radiology shielding certification and premises inspection, from 1.3.4 and 1.2.3: 2 weeks. H, IT cabling, network, and phones, from 1.5: 3 weeks. I, equipment installation, from 1.4: 2 weeks. J, final inspection and certificate of occupancy, from 1.3.6: 1 week. K, move and opening, from 1.6: 1 week.
Dependencies Given With Reasons
B, C, and E each follow A: the permit application, the equipment list, and the contractor's bid all require the finished drawings. D follows C: vendors begin manufacture when the order is placed. F follows B and E: construction cannot start without a permit and a signed contract. G follows F: shielding can be certified only when walls are finished. H follows F: cabling is installed after walls are closed and finished, to avoid damage. I follows D and F: equipment is installed when it has arrived and the rooms are finished. J follows G, H, and I: the final inspection requires all work complete. K follows J: animals cannot be housed until the certificate of occupancy is issued. A dependency without a reason is a guess, and a guess on the critical path is expensive.
Forward Pass Shown
Early start and early finish, in weeks from project start on September 8. A: 0 to 8. B: 8 to 14. C: 8 to 12. E: 8 to 12. D: 12 to 24. F: starts at the later of B's finish, 14, and E's finish, 12, so 14 to 30. G: 30 to 32. H: 30 to 33. I: starts at the later of D's finish, 24, and F's finish, 30, so 30 to 32. J: starts at the latest of G, 32, H, 33, and I, 32, so 33 to 34. K: 34 to 35. The project takes 35 weeks, finishing on May 11.
Backward Pass Shown
Late finish and late start, working back from week 35. K: late finish 35, late start 34. J: 34 and 33. G: late finish 33, late start 31. H: late finish 33, late start 30. I: late finish 33, late start 31. F: late finish is the earliest late start among G, 31, H, 30, and I, 31, so 30; late start 14. D: late finish is I's late start, 31; late start 19. C: late finish 19; late start 15. B: late finish is F's late start, 14; late start 8. E: late finish 14; late start 10. A: late finish is the earliest late start among B, 8, C, 15, and E, 10, so 8; late start 0.
Float Calculated
Total float is late start minus early start. A: 0. B: 0. C: 7. D: 7. E: 2. F: 0. G: 1. H: 0. I: 1. J: 0. K: 0.
Critical Path Derived, Not Chosen
The critical path is the chain of activities with zero float: A, B, F, H, J, K, totaling 8 plus 6 plus 16 plus 3 plus 1 plus 1, or 35 weeks. It was derived from the passes, not chosen by judgment. It shows that IT installation, not equipment installation, is critical, which is not what the team expected; cabling after the walls are finished takes one week longer than equipment installation. The Project Management Institute (2017) describes the critical path as the longest path through the network, which determines the shortest possible project duration.
Near-Critical Chains Flagged Too
Chains with little float are flagged, because a small slip would make them critical. G, shielding certification and premises inspection, and I, equipment installation, each have 1 week of float. E, bidding and award, has 2 weeks. C and D, equipment ordering and delivery, have 7 weeks, enough to absorb a moderate supplier delay but not a severe one; a delivery more than 7 weeks late would make equipment critical. One week of float on the physicist's visit means one late appointment moves the opening.
Resources Behind the Critical Path
The critical activities depend on different parties: the architect for drawings, the city for the permit, the contractor for construction, the IT vendor for cabling, the city again for final inspection, and practice staff for the move. Only the last is under the practice's direct control. That makes early, regular contact with each party the project manager's main tool for protecting the critical path.
Buffer to the Required Date
The calculated finish is May 11, and the required opening is June 1, a buffer of three weeks. The buffer belongs to the project, not to any activity, and the sponsor will be told whenever it is used.
How Durations Were Estimated
Durations come from the people who will do the work. The architect estimated 8 weeks for drawings based on similar clinic projects. The permit duration uses the city's posted review time for commercial alterations. The contractor's 16-week construction duration comes from its bid, which breaks the work down by trade. Equipment lead times come from vendor quotes. The IT vendor estimated 3 weeks for cabling, network setup, and phones. Estimates from those responsible are more reliable than estimates made by the project manager alone, and they give each party ownership of its duration.
What a Slip on the Critical Path Costs
A one-week slip on any critical activity moves the finish date by one week and uses one week of the three-week buffer. If it happens during the build-out, the contractor's site overhead adds roughly another 3,000 dollars for that week. Two slips of a week each would leave one week of buffer; a fourth week would push opening past June 1 and require the Elm Street extension.
What the Schedule Tells the Project Manager
Watch the permit review and construction weekly, since they are critical and outside the practice's control. Schedule the physicist and state inspector early, since they have 1 week of float. Ask the IT vendor whether cabling can begin during the last weeks of construction in finished rooms, which could shorten the critical path.
Conclusion
Eleven activities traced to work packages, with reasoned dependencies, produce a 35-week schedule finishing May 11. The forward and backward passes show a critical path that runs from the drawings through the permit, the build-out, cabling and phones, the city's last inspection, and moving day, with shielding certification and equipment installation near-critical at 1 week of float, and a 3-week buffer to the June 1 requirement.
References
Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK guide) (6th ed.). Project Management Institute.
What the PM FPX 4030 Assessment 1 instructions ask for
The first assessment in PM FPX 4030 asks you to build a project schedule using a network diagram. You list the activities from the work breakdown structure, estimate durations with a stated basis, identify dependencies and the reason for each, draw the network, perform the forward and backward passes to find early and late dates, calculate float, identify the critical path and discuss near-critical paths and schedule risk. The critical path should come out of the calculations, not be picked by judgment. Scheduling texts on the critical path method and the PMBOK Guide support the work.
How the PM-FPX4030 Assessment 1 example is put together
The example works in the order the calculation demands. The activity list comes first, drawn from the work packages rather than invented, so every activity traces back to something the scope promised. Dependencies follow, and each one carries a reason, since a predecessor with no justification is a guess that will not hold when the schedule is questioned. Durations arrive next with the estimating basis named for each group. The network is then drawn, and the forward pass produces early dates while the backward pass produces late dates, with the results shown rather than summarized. Float is computed per activity, and the zero-float chain is identified as the critical path. The final section states the project duration, the paths within a few days of critical, and what would happen to the end date if one critical activity slipped.
PM FPX 4030 Assessment 1 scoring guide: what Distinguished looks like
Capella's scoring guide rates the activity list, the durations, the dependencies, the passes, the float, the critical path and the risk discussion. Activities reach Distinguished when each traces to a work package, so nothing appears from nowhere. Durations score higher when their basis is stated, such as a vendor quote or past experience. Dependencies earn credit when each has a reason, like cabinets installed before the plumber connects sinks. The passes are judged on whether both are shown with their arithmetic. Float should be calculated for every activity. The critical path should be derived from zero float. Near-critical chains show awareness of risk. Proficient schedules find the critical path; Distinguished ones show why it is critical and what else could become critical.
PM FPX 4030 Assessment 1 help from the desk
Schedule papers often list activities that do not match the work breakdown structure, so the schedule and scope drift apart. Another weakness is giving dependencies without reasons, which makes the logic impossible to check. Only the forward pass is shown, so float cannot be verified. The critical path is chosen by intuition instead of calculated. Near-critical paths are ignored, although a small delay on one can make it the new critical path. Durations appear with no basis. A table with each activity, its duration, predecessors, early and late dates and float, alongside the diagram, makes every calculation visible and gives the cost baseline in Assessment 2 a solid schedule to phase against.
Get a PM FPX 4030 Assessment 1 example written to your instructions
Send the Assessment 1 instructions and the scoring guide from your PM FPX 4030 courseroom, plus the activity list or case data your section provides. We write a custom example to those criteria, with the passes calculated and the diagram reconciled against the table, and return it in 24 to 48 hours. The first custom sample is free. The paper above is an original model document written by our desk, not a submitted student paper and not an official Capella University document.
More PM FPX 4030 papers and BS in Business, Project Management samples
- PM FPX 4030 Assessment 2: Cost Baseline
- PM FPX 4030 Assessment 3: Quality Management Plan
- PM FPX 4040 Assessment 1: Responsibility Assignment Matrix
- PM FPX 4020 Assessment 1: Project Charter
- PM FPX 4050 Assessment 1: Stakeholder Analysis
- PM FPX 4000 Assessment 1: Project Brief
PM FPX 4030 Assessment 1 questions, answered
Do I have to draw the diagram by hand?
Check your instructions, since some sections accept scheduling software output and others want a drawn network. Either way the node values have to be present and correct. Software that hides the early and late dates makes the calculation criterion harder to satisfy, so export a view that shows them or add a table with the same figures alongside.
What if my critical path has two chains of equal length?
That is a legitimate result and worth saying out loud. Two parallel chains at zero float means two paths can each delay the project, which doubles the number of activities the manager has to watch. State both, mark both on the diagram, and note the management consequence rather than picking one and hoping nobody checks the other.
Where do the durations come from if this is a made-up project?
From a stated estimating basis you apply consistently. Analogous reasoning from similar work, a parametric rate per unit, or a three-point estimate all give you defensible numbers, and naming which one you used satisfies the supporting criterion. Numbers that appear without any basis are the weakest part of most submissions, even when the arithmetic on them is flawless.
Where can I find a free PM FPX 4030 Assessment 1 sample paper?
Every step of the relocation schedule appears here: activities traced to work packages, dependencies with reasons, both passes shown, float calculated and near-critical chains flagged.
What is float in PM FPX 4030 Assessment 1?
The amount of time an activity can slip without delaying the project, found by subtracting the early start from the late start. Activities with zero float form the critical path.