Free sample paper for PM FPX 4050 Assessment 3
A Status Report on a Veterinary Hospital Relocation: Health Stated in the First Line, Progress Measured Against Baseline, Risks and Issues Kept Apart, the Bad News Early, and Decisions Requested
Student Name
Capella University
PM FPX 4050: Communication and Stakeholder Management
Instructor Name
Month Day, Year
Health Stated in the First Line
Status as of January 16: yellow. The schedule is at risk of a one-week slip after an electrical service upgrade was required; the budget is on track, but contingency has fallen from 84,500 to 43,300 dollars. Two decisions are needed from the sponsor by January 23.
Summary
To: Dr. Karen Walsh, Sponsor. From: Jennifer Moore, Project Manager. Reporting period: December 15 to January 16. The report follows the format agreed in the communication plan, with bad news first. The Project Management Institute (2017) describes work performance reports as the means of communicating status against the plan to support decisions; this report is written for that purpose.
The Bad News Arrives Early
The bad news comes before the progress summary. During demolition on January 5, the contractor found that the building's 200-amp electrical service cannot support the surgical lights, anesthesia equipment, digital X-ray, and heating and cooling load together. The city requires an upgrade to 400-amp service. The sponsor approved change order 3 on January 9 for 38,000 dollars. The utility has scheduled the new service connection for February 20, which on the current sequence would delay construction completion by about three weeks. The contractor has proposed resequencing interior work so that most of the delay is absorbed; with the resequencing, the expected slip is one week, moving the forecast opening from May 11 to May 18 and leaving a two-week buffer to the required June 1 date. The sponsor should read about the electrical problem in the first paragraph, not discover it on page two.
Progress Measured Against Baseline
Milestones against baseline: design frozen, baseline November 3, actual November 3, on time. City building permit, baseline December 15, actual December 18, three days late. Construction start, baseline December 15, actual December 18, three days late. Equipment orders placed, baseline December 1, actual November 28, on time. Construction completion, baseline April 6, forecast April 13 with resequencing. Opening, baseline May 11, forecast May 18. Cost against baseline: planned spending through December was 217,000 dollars; actual spending was 219,400 dollars, 1.1% above plan, due to a higher permit fee than estimated. Change orders approved: three, totaling 41,200 dollars, all funded from contingency; change orders 1 and 2, for a relocated floor drain and an added outlet, totaled 3,200 dollars, and change order 3 is 38,000 dollars. Contingency remaining: 43,300 dollars of 84,500. Management reserve: 60,000 dollars, untouched.
Issues This Period
Issues are events that have already happened and need management. Issue 1: the electrical service upgrade, handled through change order 3 and the resequencing proposal below. Issue 2: the permit was issued three days late, delaying construction start; absorbed within the resequencing. Issue 3: the county emergency hospital has changed its manager, and the agreement to take Maple Ridge's emergencies during the move must be reconfirmed; the project manager has a meeting on January 22.
Risks Kept Apart From Issues
Risks are events that may happen. Risk 1: the digital X-ray vendor has warned of possible delays in detector shipments; the unit could arrive up to three weeks late. Current float on equipment is seven weeks, so a three-week delay would not affect opening, but it would reduce training time. Risk 2: the Elm Street lease extension is still not signed; with the forecast slip, the buffer is two weeks, and a second slip would make the extension essential. Risk 3: remaining contingency of 43,300 dollars may not cover further hidden conditions in the rear of the building, which has not been fully opened. The contractor estimates 20,000 to 35,000 dollars of exposure.
Decisions Requested, Not Implied
Decision 1, needed by January 23: approve the contractor's resequencing plan, which requires about 6,000 dollars of weekend overtime from contingency to recover two of the three weeks. Recommendation: approve. Without it, the forecast opening is June 1, with no buffer. Decision 2, needed by January 23: authorize the project manager to offer the Elm Street landlord a 10% rent premium, about 950 dollars a month, for a signed option to extend month to month through August. Recommendation: approve. The cost of the option is small compared with the risk of having no place to see patients. Decision 3, for information: if further hidden conditions exceed remaining contingency, the project manager will ask for release of management reserve at that time. A report that ends with "please advise" leaves the sponsor to guess what is being asked.
What the Sponsor Does Not Need to Worry About
Some items are on track and need no attention: equipment orders were placed early and are within quote validity; the IT vendor has confirmed its installation dates; staff communication is on schedule, with the first move briefing at the January staff meeting; and the neighbor has not raised further concerns since receiving the owner's letter.
Trend Since the Last Report
Compared with the December report, overall status has moved from green to yellow because of the electrical upgrade. Cost variance has grown from 0.4% to 1.1% above plan, both driven by permit fees. Schedule variance has moved from zero to a forecast one-week slip. If both decisions are approved, the project manager expects to return the status to green by the February report, once the resequenced work is underway and the lease option is signed.
How Forecasts Were Made
The one-week forecast slip comes from the contractor's revised schedule, which the architect reviewed and found reasonable. It assumes the utility keeps its February 20 connection date. If the utility slips by a week, the opening forecast moves by a week as well, and the report will say so the day the utility confirms or changes its date.
Next Period
Planned activities through February 15: framing and rough-in plumbing; electrical rough-in in areas not dependent on the new service; resequenced interior work; confirmation of the emergency hospital agreement; client notice planning; and booking the physicist's shielding survey for the first week of April.
Conclusion
The project is yellow. The electrical upgrade has cost 38,000 dollars and threatens a three-week slip, reduced to one week with resequencing. Progress against baseline shows milestones on time or a few days late and spending 1.1% above plan. Issues and risks are listed separately, and the sponsor is asked to approve resequencing overtime and a lease extension option by January 23.
References
Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK guide) (6th ed.). Project Management Institute.
The Capella PM FPX 4050 Assessment 3 instructions
The final assessment in PM FPX 4050 asks you to write a status report for a project. You state the overall health, summarize accomplishments against the plan, report schedule and cost performance against the baseline, list issues that need attention now, list risks that may become issues, request any decisions needed from the sponsor and forecast completion. The report should put the most important information first, since many readers stop after the first paragraph, and it should follow the format agreed in the communications plan. Bad news should be reported clearly and early. Project communication texts and earned value concepts support the report.
How the PM-FPX4050 Assessment 3 example is put together
The example is ordered by what the reader needs first. The health summary opens the document and carries the exception with it, so a sponsor who reads one paragraph still knows the project is late on integration testing. Accomplishments follow, stated as deliverables completed against planned dates rather than as activity. The next section covers upcoming work with the dates it depends on. Budget comes after, expressed against baseline with a variance and a cause. Risks and issues sit together but are labeled separately, and each carries an owner and a next action. Decisions required is its own section near the end, phrased as questions with options attached, because a report that asks for nothing tends to get no response. A short appendix carries the detail the delivery team wants and the sponsor does not.
Reading the PM FPX 4050 Assessment 3 scoring guide
Marks go to the health statement, the progress measurement, the issues and risks, the decisions and the forecast. Health reaches Distinguished when stated in the first line with the main exception. Progress scores higher when measured against the baseline, such as percent of work complete versus planned. Issues and risks earn credit when kept separate. Decisions are judged on whether each is stated as a request with a deadline. Forecasts should explain their basis, for example the rate of progress over the last three weeks. Trends should be shown, so the sponsor can see whether performance is improving or getting worse since the last report. Distinguished reports let a sponsor understand the project in one minute and know exactly what is being asked of them.
PM FPX 4050 Assessment 3 help from the desk
Status reports often open with a list of accomplishments and bury the delay in the fourth paragraph. Another weakness is reporting activity rather than progress against the baseline. Risks and issues are mixed together, so the sponsor cannot tell what is happening now from what might happen. Decisions are implied rather than requested. Forecasts appear with no basis. Trends are missing, so the sponsor cannot tell whether things are improving. Opening with a one-line health statement and the single most important exception, then following a consistent format, makes the report quick to read and closes the course with a document a sponsor would value.
Get a PM FPX 4050 Assessment 3 example written to your instructions
Send the Assessment 3 instructions and the scoring guide from your PM FPX 4050 courseroom, plus the scenario and any reporting template your section requires. We produce a custom example to those criteria, written as a real report with an exception in it and a decision requested, and return it in 24 to 48 hours. The first is free. The paper above is an original model document written by our desk, not a submitted student paper and not an official Capella University document.
More PM FPX 4050 papers and BS in Business, Project Management samples
- PM FPX 4050 Assessment 1: Stakeholder Analysis
- PM FPX 4050 Assessment 2: Communications Plan
- PM FPX 4060 Assessment 3: Risk Response Plan
- PM FPX 4040 Assessment 3: Motivation Analysis
- PM FPX 4070 Assessment 3: Procurement Plan
- PM FPX 4030 Assessment 3: Quality Management Plan
PM FPX 4050 Assessment 3 questions, answered
Should the report say the project is behind?
Yes, when it is. In current courserooms the scenario usually contains a problem on purpose, and a report that returns an untroubled green has missed the exercise. State the variance, name the cause, give the recovery option and say what it costs. Faculty read that as professional judgment, while a clean report with a buried problem reads as avoidance.
Who is the audience for the report in this assessment?
Read the instructions, since some sections name a sponsor, a steering group or a client. Where the audience is open, choose one and say so at the top, because tone, level of detail and the decisions requested all change with the reader. A single report written for everyone tends to lose the criterion that carries the course theme.
Can I include charts or a dashboard?
Yes, if they carry information the prose would otherwise spend a paragraph on. A milestone bar, a variance figure or a simple health table all work, provided each one is labeled and referenced in the text. What does not work is decoration: colored graphics with no baseline, no period and no source leave a reader unable to check anything.
Where can I find a free PM FPX 4050 Assessment 3 sample paper?
This page holds a finished status report for the relocation, with health stated in the first line, progress against baseline, risks kept apart from issues, bad news early and decisions requested.
Should the status report say the project is behind in PM FPX 4050 Assessment 3?
Yes, clearly and early. Sponsors can act on bad news when they hear it in time, and a report that hides a delay loses their trust when the delay surfaces.