| Course | PM FPX 4070 Procurement Management in Project Management |
|---|---|
| Assessment | Assessment 3 |
| Paper type | Procurement plan |
| Length | About 1,110 words, 5 pages |
| Format | APA 7 student paper |
| School | Capella University |
| Program | BS in Business, Project Management |
| Updated | September 2026 |
Free sample paper for PM FPX 4070 Assessment 3
Choosing the Contract and Vendor for a Veterinary Hospital's Network Installation: Contract Type Argued From Risk, Rejected Options Written Down, Weighted Selection Criteria, Performance Measured After Signature, Invoices Tied to Verified Progress, and Closure Defined First
Student Name
Capella University
PM FPX 4070: Procurement Management in Project Management
Instructor Name
Month Day, Year
Contract Type Argued From Risk
The work is defined in a statement of work with 64 data drops, specified equipment, and test-based acceptance, so the scope is clear and the vendor can estimate it well. When scope is clear, a firm fixed-price contract places cost risk on the vendor, who is best placed to manage its own labor and materials. The practice's main risks are schedule and quality, not cost, and those are addressed through acceptance tests and payment terms rather than the contract type. The Project Management Institute (2017) notes that fixed-price contracts suit well-defined requirements, while cost-reimbursable contracts suit work whose scope is uncertain. A firm fixed-price contract is chosen, with unit prices for any added drops or access points.
Rejected Options Written Down
Time and materials was rejected because it would leave the practice carrying cost risk on work that is well defined, and because the practice has no one with the expertise to judge whether hours billed are reasonable. Cost plus a fixed fee was rejected for the same reason and because it adds administrative work. A fixed price with an incentive for early completion was considered, since the work is on the critical path, but rejected because the vendor cannot start until the general contractor finishes each area, so the vendor does not control the main driver of early completion. An incentive for early finish means little when someone else controls when the work can start.
Selection Criteria Carry Weights
Three vendors submitted proposals. Criteria and weights were set before proposals were opened: price, 30%; experience with medical or veterinary clinic installations, 25%; ability to commit two technicians for weeks 31 to 33, 20%; quality of the proposed approach and test plan, 15%; references from two clients of similar size, 10%. Vendor A: price 90,000 dollars, score 4; experience, three veterinary clinics in two years, score 5; technicians confirmed, score 5; approach, detailed test plan, score 4; references, strong, score 5. Weighted contributions: price 1.20, experience 1.25, technicians 1.00, approach 0.60, references 0.50; total 4.55. Vendor B: price 78,000 dollars, score 5; experience, mainly offices, score 3; technicians, one confirmed and one to be hired, score 2; approach, general, score 3; references, good, score 4. Weighted contributions: price 1.50, experience 0.75, technicians 0.40, approach 0.45, references 0.40; total 3.50. Vendor C: price 104,000 dollars, score 3; experience, hospitals, score 5; technicians confirmed, score 5; approach, detailed, score 5; references, strong, score 5. Weighted contributions: price 0.90, experience 1.25, technicians 1.00, approach 0.75, references 0.50; total 4.40. Vendor A is selected. Vendor B's lower price does not offset the risk of an unconfirmed technician on critical path work.
Negotiation Before Signature
Before signing, the practice negotiated two points with Vendor A. The vendor's draft contract limited its warranty to 30 days; the practice required 90 days, matching the statement of work, and the vendor agreed. The vendor's payment terms asked for 50% on signing; the practice held to payment on verified progress, and the vendor accepted the milestone schedule below in exchange for payment within 15 days of each verified milestone rather than 30.
Risks the Contract Leaves With the Practice
The contract does not remove every risk. The vendor cannot start in an area until the general contractor finishes it, so delays by the contractor pass through to the network work; the practice manages this through the construction schedule. The internet service line is provided by the practice's carrier, not the vendor, and a late carrier installation would delay testing; the practice ordered the line eight weeks ahead to reduce this risk.
Performance Measured After Signature
Performance is measured after signature, not only at selection. The vendor reports progress at each weekly site meeting during installation: drops installed and certified, equipment installed, and tests passed. Measures: percentage of drops certified by the end of week 32, target 100%; defects found at acceptance testing, target fewer than 5 drops failing certification on first test; response to issues within one business day. Failures to meet these are recorded and discussed with the vendor's project lead the same week.
Invoices Tied to Verified Progress
Payments are tied to verified progress. 20% on delivery of network equipment and phones to the site, verified by the practice manager against the packing list. 40% when all 64 drops pass certification, verified by the test report. 30% on acceptance of all deliverables D2 through D7. 10% retained until 30 days after opening, released if no workmanship defects remain open. No payment is made against hours worked or effort claimed.
Why Vendor C Was Not Chosen
Vendor C scored nearly as well as Vendor A and has hospital experience, but its price was 14,000 dollars higher, above the 90,000 dollar budget for this component, and its approach offered no advantage for a building of this size. Vendor C was thanked and told its proposal was competitive, which keeps it available for future work or if Vendor A cannot perform.
Handling a Vendor Failure
If Vendor A fails to meet the schedule or quality measures and does not correct the problem within five business days of written notice, the contract allows the practice to terminate for cause and engage another vendor, with Vendor A responsible for added costs. Vendor C's proposal remains on file as the fallback.
Closure Defined Before the Work Starts
Closure is defined now. The contract is closed when: all deliverables are accepted in writing; the as-built documentation and credentials are delivered; the retained 10% is released after 30 days with no open defects; the warranty period is recorded in the practice's asset records; and a brief vendor performance review is filed for future procurement. The Project Management Institute (2017) describes closing procurements as confirming that all work and deliverables are accepted and that administrative requirements are complete. Defining closure at the start means both sides know what finished looks like before anyone is tired of the job.
Conclusion
A firm fixed-price contract is chosen because scope is clear and cost risk belongs with the vendor; time and materials, cost plus fee, and an early-completion incentive are rejected with reasons. Weighted criteria select Vendor A over a cheaper vendor with staffing risk. Performance is tracked weekly, payments follow verified progress with 10% retained, and closure conditions are set before work begins.
References
Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK guide) (6th ed.). Project Management Institute.
What the PM FPX 4070 Assessment 3 instructions ask for
The final assessment in PM FPX 4070 asks you to plan how the procurement will be carried out and controlled. You choose a contract type, such as fixed price, cost reimbursable or time and materials, and justify it from the stability of the requirement and the risks, state why other types were rejected, set weighted criteria for selecting a vendor, apply them, describe negotiation, plan how performance will be measured after signing, tie payments to verified progress and define how the contract will be closed. The plan follows PMI guidance on conducting and controlling procurements.
How the PM-FPX4070 Assessment 3 example is put together
The plan runs from decision to control. It opens with the procurement objective and what is in scope, then treats contract type as the first real question, because everything downstream depends on it. That section describes the requirement's stability, names the risks the project cannot control, and reasons toward a type on that basis, with the alternatives rejected in writing. Selection comes next: criteria, weights, the evidence sought, the evaluation panel and how a tie is broken. Solicitation follows, covering the documents issued and the timetable. Contract administration takes the second half of the document: kick-off, progress verification, invoice approval, performance measures with thresholds, and the escalation path when a measure is missed. A change and dispute section states how variations are handled. Closure terms and lessons capture end the plan.
PM FPX 4070 Assessment 3 scoring guide: what Distinguished looks like
Marks go to the contract type, the rejected options, the selection criteria, the evaluation, the performance management, the payment terms and closure. The contract type reaches Distinguished when argued from risk, since the type decides who bears the cost of surprises. Rejected options score higher when written down with reasons. Criteria earn credit when weighted before vendors are scored. The evaluation is judged on whether the losing vendors' scores are explained. Performance should be measured after signature. Payments should be tied to verified progress, with each invoice matched to an accepted milestone. Closure should be defined from the start, including final acceptance, retained payment and the handover of documentation. Distinguished plans carry the procurement from choice to closeout.
PM FPX 4070 Assessment 3 help from the desk
Procurement plans often choose a fixed-price contract as the safe default without asking whether the requirement is stable enough. Another weakness is scoring vendors on criteria that were not weighted in advance. Rejected vendors are not explained. The plan ends at signature, leaving performance and payment unmanaged. Invoices are paid on schedule rather than on progress. Closure is left undefined, so nobody knows when the vendor's obligations end or when the final payment is due. A weighted scoring table for the vendors, followed by a short schedule of milestones, checks and payments, carries the plan past the signature and closes the course with procurement managed from start to finish.
Get a PM FPX 4070 Assessment 3 example written to your instructions
Email the Assessment 3 instructions and the scoring guide from your PM FPX 4070 courseroom, plus the scenario and anything already fixed about the purchase. We write a custom example to those criteria, with the contract type argued from risk allocation and weighted selection criteria included, and return it in 24 to 48 hours. The first sample is free. The paper above is an original model document written by our desk, not a submitted student paper and not an official Capella University document.
More PM FPX 4070 papers and BS in Business, Project Management samples
- PM FPX 4070 Assessment 1: Make-or-Buy Analysis
- PM FPX 4070 Assessment 2: Statement of Work
- PM FPX 4080 Assessment 3: Retrospective Report
- PM FPX 4060 Assessment 3: Risk Response Plan
- PM FPX 1000 Assessment 3: Constraint Analysis
- PM FPX 4050 Assessment 3: Status Report
PM FPX 4070 Assessment 3 questions, answered
Which contract type is the safest choice for this assessment?
None of them, and choosing on safety is the error the criterion catches. Firm fixed price fits a requirement you can specify completely and hands the overrun to the supplier at a premium. Cost reimbursable fits work that cannot be defined yet and keeps the overrun with the buyer. Argue from the requirement in front of you.
Does the plan cover what happens after a supplier is chosen?
It should, and in many sections that half carries its own criterion. Selection is one section; administration is the rest. Say who verifies progress, how invoices are approved against accepted work, what performance measures are tracked, how often the supplier is reviewed and what the project does when a threshold is missed.
How much of the earlier procurement work can I reuse?
The scenario and the decision to buy, stated briefly, and nothing else. The make-or-buy analysis answered whether to purchase, and the statement of work said what the supplier delivers. This plan governs the purchase itself, so space spent restating either one comes out of contract type, selection and administration, where the criteria actually sit.
Where can I find a free PM FPX 4070 Assessment 3 sample paper?
You can read the whole procurement plan for the network installation here, with the contract type argued from risk, rejected options written down, weighted criteria and invoices tied to verified progress.
Which contract type is safest in PM FPX 4070 Assessment 3?
None is safe in every case. Fixed price protects the buyer when the requirement is clear, while cost reimbursable suits uncertain work. The choice should follow from the risks.